• HOME
  • NEWS
  • EXPLORE
    • CAREER
      • Companies
      • Jobs
    • EVENTS
    • iGEM
      • News
      • Team
    • PHOTOS
    • VIDEO
    • WIKI
  • BLOG
  • COMMUNITY
    • FACEBOOK
    • INSTAGRAM
    • TWITTER
Saturday, February 7, 2026
BIOENGINEER.ORG
No Result
View All Result
  • Login
  • HOME
  • NEWS
  • EXPLORE
    • CAREER
      • Companies
      • Jobs
        • Lecturer
        • PhD Studentship
        • Postdoc
        • Research Assistant
    • EVENTS
    • iGEM
      • News
      • Team
    • PHOTOS
    • VIDEO
    • WIKI
  • BLOG
  • COMMUNITY
    • FACEBOOK
    • INSTAGRAM
    • TWITTER
  • HOME
  • NEWS
  • EXPLORE
    • CAREER
      • Companies
      • Jobs
        • Lecturer
        • PhD Studentship
        • Postdoc
        • Research Assistant
    • EVENTS
    • iGEM
      • News
      • Team
    • PHOTOS
    • VIDEO
    • WIKI
  • BLOG
  • COMMUNITY
    • FACEBOOK
    • INSTAGRAM
    • TWITTER
No Result
View All Result
Bioengineer.org
No Result
View All Result
Home NEWS Science News Biology

Construction delays make new nuclear power plants costlier than ever

Bioengineer by Bioengineer
May 29, 2018
in Biology
Reading Time: 2 mins read
0
Share on FacebookShare on TwitterShare on LinkedinShare on RedditShare on Telegram

The cost of building new nuclear power plants is nearly 20 per cent higher than expected due to delays, a new analysis has found.

A new analysis of the history of nuclear power plant projects shows since 2010 delays have contributed 18 per cent the costs.

These delays – which can run into years or even decades – increase the cost compared with older projects and are often overlooked when new projects are planned. The authors say that these extra costs need to be properly assessed when considering new nuclear projects.

They say nuclear projects are more like 'mega-projects', such as large dams, which require more rigorous financial assessments due to their high uncertainty and risk.

In the study, published today in the journal Energy Policy, the authors also suggest that because these delay costs make nuclear projects high risk, decision makers might instead focus on more low-risk low-carbon technologies such as wind or solar power.

When assessing the cost of new nuclear projects, decision makers often use 'overnight construction costs', which assume the project is built on time, usually within five years. However, the 'lead-time' – the time between initiation of the project and completion – can cause significant extra costs.

The research team, from Imperial College London, the Universidade Federal do Rio de Janeiro and the University of Minho, looked at total costs of nuclear projects between 1955-2016, including delay costs.

Usually, as technologies mature and experience is gained in construction, costs come down. However, the team found that for nuclear, there has been a blip in the learning curve, with costs currently increasing, especially for projects since 2010.

Lead author Dr Joana Portugal Pereira, from the Centre for Environmental Policy at Imperial, said: "Nuclear projects are actually becoming more complex to carry out, inducing delays and higher costs. Safety and regulatory considerations play heavily into this, particularly in the wake of the 2011 Fukushima Dai-ichi nuclear accident in Japan."

The analysis is one of the first to assess full financial costs of building nuclear projects throughout time, and not just the 'overnight' costs. It also looked at projects around the world, including newer nuclear builders like China, India, and the UAE, rather than just the traditional builders in Europe, the USA and Japan.

They say that while nuclear projects can help bridge the gap between fossil fuels and renewable energy, they could hinder progress if projects stall.

Dr Portugal Pereira said: "If we want to decarbonise our energy system, nuclear may not be the best choice for a primary strategy. Nuclear power is better late than never, but to really address climate change, it would be best if they were not late at all, as technologies like wind and solar rarely are."

###

Media Contact

Hayley Dunning
[email protected]
020-759-42412
@imperialspark

http://www3.imperial.ac.uk/college/news

https://www.imperial.ac.uk/news/186487/construction-delays-make-nuclear-power-plants/

Related Journal Article

http://dx.doi.org/10.1016/j.enpol.2018.05.041

Share12Tweet8Share2ShareShareShare2

Related Posts

Florida Cane Toad: Complex Spread and Selective Evolution

Florida Cane Toad: Complex Spread and Selective Evolution

February 7, 2026
New Study Uncovers Mechanism Behind Burn Pit Particulate Matter–Induced Lung Inflammation

New Study Uncovers Mechanism Behind Burn Pit Particulate Matter–Induced Lung Inflammation

February 6, 2026

DeepBlastoid: Advancing Automated and Efficient Evaluation of Human Blastoids with Deep Learning

February 6, 2026

Navigating the Gut: The Role of Formic Acid in the Microbiome

February 6, 2026
Please login to join discussion

POPULAR NEWS

  • Robotic Ureteral Reconstruction: A Novel Approach

    Robotic Ureteral Reconstruction: A Novel Approach

    82 shares
    Share 33 Tweet 21
  • Digital Privacy: Health Data Control in Incarceration

    63 shares
    Share 25 Tweet 16
  • Study Reveals Lipid Accumulation in ME/CFS Cells

    57 shares
    Share 23 Tweet 14
  • Breakthrough in RNA Research Accelerates Medical Innovations Timeline

    53 shares
    Share 21 Tweet 13

About

We bring you the latest biotechnology news from best research centers and universities around the world. Check our website.

Follow us

Recent News

Evaluating Pediatric Emergency Care Quality in Ethiopia

TPMT Expression Predictions Linked to Azathioprine Side Effects

Improving Dementia Care with Enhanced Activity Kits

Subscribe to Blog via Email

Success! An email was just sent to confirm your subscription. Please find the email now and click 'Confirm' to start subscribing.

Join 73 other subscribers
  • Contact Us

Bioengineer.org © Copyright 2023 All Rights Reserved.

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In
No Result
View All Result
  • Homepages
    • Home Page 1
    • Home Page 2
  • News
  • National
  • Business
  • Health
  • Lifestyle
  • Science

Bioengineer.org © Copyright 2023 All Rights Reserved.