• HOME
  • NEWS
  • EXPLORE
    • CAREER
      • Companies
      • Jobs
    • EVENTS
    • iGEM
      • News
      • Team
    • PHOTOS
    • VIDEO
    • WIKI
  • BLOG
  • COMMUNITY
    • FACEBOOK
    • INSTAGRAM
    • TWITTER
Friday, August 29, 2025
BIOENGINEER.ORG
No Result
View All Result
  • Login
  • HOME
  • NEWS
  • EXPLORE
    • CAREER
      • Companies
      • Jobs
        • Lecturer
        • PhD Studentship
        • Postdoc
        • Research Assistant
    • EVENTS
    • iGEM
      • News
      • Team
    • PHOTOS
    • VIDEO
    • WIKI
  • BLOG
  • COMMUNITY
    • FACEBOOK
    • INSTAGRAM
    • TWITTER
  • HOME
  • NEWS
  • EXPLORE
    • CAREER
      • Companies
      • Jobs
        • Lecturer
        • PhD Studentship
        • Postdoc
        • Research Assistant
    • EVENTS
    • iGEM
      • News
      • Team
    • PHOTOS
    • VIDEO
    • WIKI
  • BLOG
  • COMMUNITY
    • FACEBOOK
    • INSTAGRAM
    • TWITTER
No Result
View All Result
Bioengineer.org
No Result
View All Result
Home NEWS Science News

LRT, REM, mass transit projects and their fuzzy reality

Bioengineer by Bioengineer
August 17, 2023
in Science News
Reading Time: 4 mins read
0
Share on FacebookShare on TwitterShare on LinkedinShare on RedditShare on Telegram

The city of Gatineau is planning a tramway network that will link up with Ottawa, where the Light Rail Transit (LRT) continues to be bogged down by major mishaps. With Montreal’s new Réseau express métropolitain (REM) light transit system experiencing its own hiccups to start, how can cities looking to incorporate mass transport systems successfully launch such endeavors while avoiding project failures and years of misfortune?

LRT, REM, mass transit projects and their fuzzy reality

Credit: Telfer School of Management, University of Ottawa

The city of Gatineau is planning a tramway network that will link up with Ottawa, where the Light Rail Transit (LRT) continues to be bogged down by major mishaps. With Montreal’s new Réseau express métropolitain (REM) light transit system experiencing its own hiccups to start, how can cities looking to incorporate mass transport systems successfully launch such endeavors while avoiding project failures and years of misfortune?

New research from a University of Ottawa professor suggests project leaders not overlook the “F” word.

Telfer School of Management professor Lavagnon Ika found a lack of full appreciation of the context surrounding the delivery of large-scale public mass transit projects is detrimental to their performance. In particular, the elusive or changing nature of these projects’ goals, their shifting scope, and the conflicting expectations of their stakeholders lead to the biggest problems. Managing this fuzziness rather than delivering within budget is the most important role of project managers.

“There is a solution to time overruns, cost blowouts, business case failures, and users’ dismay,” says Professor Ika, who looked into transit projects in his study and also recently published a book on the topic based on his research on 3,000 projects. “Managing fuzziness requires a shift from a narrow focus on time, cost, and scope to a comprehensive approach that considers the rational, psychosocial, and political dimensions of projects.”

Professor Ika, Founding Director of the Observatory of Major Projects at Telfer, provides insight into this research, which considers the rational, political and dimensions that would benefit the next stages of the Ottawa LRT, the upcoming Gatineau Tramway, and the Montreal REM.

Question: What is the common theme to understanding why these mass public transport projects succumb to complications?
Lavagnon Ika:
“Managers often approach these projects in a standard way, focusing on being on time and on budget while ignoring their sociopolitical dimensions and societal impacts. Soon enough they realize the politics surrounding the project will trump their plans, even if the delivery of benefits for users and society is what matters most.

“With the LRT, then Ottawa Mayor Watson pegged its budget to a number – $2.1 billion – before planning and design were completed. Prematurely announcing an optimistic budget publicly was a political move that led to poor decisions, like excluding platform doors from the design, which later backfired in that passengers interfered with the doors, thereby jamming the platforms, and causing major delays in their commute, as revealed in the inquiry report. Planners and managers also tend to overlook stakeholder expectations and political repercussions in and around the core project team, only to realize that politics ultimately trumps the plans.”

Q: You mention expectations around the “F word”; why is fuzziness so pertinent?
L.I.: “The degree of fuzziness is at its highest when multiple principals with differing agendas and several agents with conflicting expectations are involved. They may strongly influence the project’s major stages, starting with the mandate’s initial formulation, which can significantly evolve over time. This may change unexpectedly following an election, also, which provides a new political dimension.”
 

Q: What kind of solution do you propose?
L.I.:
“A holistic approach prioritizes overall effectivity (societal benefits) over effectiveness (for formal clients) and efficiency (resource utilization). It also suggests conducting premortems and engaging a very broad array of stakeholders for better planning and decision-making.

“Overall, there is a need for a paradigm shift in transit project management, emphasizing the importance of societal impact, stakeholder engagement, and a comprehensive understanding of the project’s context and sociopolitical complexity.”

Q: What can these projects ultimately do to be a success?
L.I.:
“Drawing from extensive research on “fuzzy projects” which involved evolving goals and diverse stakeholders, early and continuous engagement with transit users is key. Additionally, non-users must be involved as they are overlooked despite being the largest group affected as taxpayers but also because they will benefit from reduced traffic, pollution, and urban revitalization.

“There are three practical recommendations for managing the cost performance of projects:

  1. Benchmarking projects.
  2. Recalibrating cost estimates at the business case phase.
  3. Reassessing how contingency is produced and evaluated.

 

“If progress is to be made to improve the cost performance of transport infrastructure projects, then standard definitions and terminologies must be enacted to better understand context and meaning surrounding projects. Then, evidence-based decisions surrounding risk can be enacted.”
 

Professor Lavagnon Ika is co-author of Managing Fuzzy Projects in 3D: A Proven, Multi-Faceted Blueprint for Overseeing Complex Projects and one of the co-authors of Large-Scale Transport Infrastructure Project Performance: Generating a Narrative of Context and Meaning, published in IEEE Transactions of Engineering Management, August 2023.



Journal

IEEE Transactions on Engineering Management

DOI

10.1109/TEM.2021.3094511

Method of Research

Case study

Subject of Research

Not applicable

Article Title

Large-Scale Transport Infrastructure Project Performance: Generating a Narrative of Context and Meaning

Article Publication Date

3-Aug-2023

Share12Tweet8Share2ShareShareShare2

Related Posts

blank

HBA Gene Variations Aid Tibetan Sheep in High Altitude

August 29, 2025

Inhibiting Protein Control Pathway Reduces Rhabdomyosarcoma Growth in Mice

August 29, 2025

Microscopy Breakthrough: Visualizing Lipids Inside Cells

August 29, 2025

Common Anti-Inflammatory Drug Shows Promise in Slowing Blood Cell Mutation Linked to Cardiovascular Disease Risk

August 29, 2025

POPULAR NEWS

  • blank

    Breakthrough in Computer Hardware Advances Solves Complex Optimization Challenges

    151 shares
    Share 60 Tweet 38
  • Molecules in Focus: Capturing the Timeless Dance of Particles

    142 shares
    Share 57 Tweet 36
  • New Drug Formulation Transforms Intravenous Treatments into Rapid Injections

    116 shares
    Share 46 Tweet 29
  • Neuropsychiatric Risks Linked to COVID-19 Revealed

    82 shares
    Share 33 Tweet 21

About

We bring you the latest biotechnology news from best research centers and universities around the world. Check our website.

Follow us

Recent News

HBA Gene Variations Aid Tibetan Sheep in High Altitude

Inhibiting Protein Control Pathway Reduces Rhabdomyosarcoma Growth in Mice

Microscopy Breakthrough: Visualizing Lipids Inside Cells

  • Contact Us

Bioengineer.org © Copyright 2023 All Rights Reserved.

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In
No Result
View All Result
  • Homepages
    • Home Page 1
    • Home Page 2
  • News
  • National
  • Business
  • Health
  • Lifestyle
  • Science

Bioengineer.org © Copyright 2023 All Rights Reserved.